Project Cargo Logistics Solution

LP-Case-Study-Icon-Vard

This case study is an example of a Project Cargo solution implemented by Logistics Plus for a global shipyard company. A summary is provided below. If you’d like to download and read the complete case study, click here, or click the thumbnail image below.

Business Profile

  • LP-Case-Study-Vard-Promar2_ThumbnailVard Promar S.A., part of the Fincantieri Group, is one of the leading shipyards in Brazil specializing in building offshore supply vessels and gas carriers.

Business Challenge

  • Client had to urgently deliver 2 thrusters and parts from Rauma, Finland to Tulcea, Romania. Logistics Plus has trucked flanges before, but at 4.6 meter height and 49 metric ton weight, that was just not an option in this case.

Logistics Plus® Solution

  • Logistics Plus Belgium BVBA used its expertise and resources to develop a project plan, contract the necessary carriers, and manage every aspect of the project from beginning to end.

Results

  • As a result of good planning and smart transport engineering, Logistics Plus managed to deliver these thrusters from Rauma to Tulcea via Antwerp in just 17 days (February 2nd to 19th) – a speed of delivery that can’t be beaten.